GERC Approves Settlement For 2 MW Solar Captive Power Project Dispute In Gujarat

In a recent decision dated February 2, 2026, the Gujarat Electricity Regulatory Commission (GERC) addressed a dispute between M/s Ultra Denim Limited and Dakshin Gujarat Vij Company Limited (DGVCL) concerning […]

The post GERC Approves Settlement For 2 MW Solar Captive Power Project Dispute In Gujarat appeared first on SolarQuarter.

  •  

CERC Orders Payment For 250 MW Solar Project Compensation

The Central Electricity Regulatory Commission (CERC) has ruled in favor of Solairepro Urja Private Limited in a long-standing dispute over unpaid compensation. The case, Petition No. 517/MP/2024, involved NTPC Limited […]