Petition of Hatsun Agro Product Limited for seeking directions upon MSEDCL to allow Net Metering β EQ
Summary:
β
### **1. BACKGROUND & CONTEXT**
HAPL operates a manufacturing plant in Solapur, Maharashtra, and is an MSEDCL consumer (Consumer No. 341629059470). It had installed a **983 kW rooftop solar system** under a **Net Metering Agreement** with MSEDCL (executed August 2022). HAPL also entered into **Power Purchase Agreements (PPAs)** for captive renewable energy supply through open access.
The dispute arose because after availing **Open Access** for its offsite renewable power, MSEDCL **refused to allow Net Metering** for HAPLβs rooftop solar generation, instead treating it on a **Gross Metering basis** from November 2023 onward. This resulted in significant financial loss to HAPL.
β
### **2. HAPLβS MAIN PRAYERS**
1. Direct MSEDCL to treat HAPLβs rooftop solar system under **Net Metering** arrangement.
2. Grant **retrospective adjustment** of amounts paid from the start of Open Access (November 2023) based on Net Metering.
β
### **3. KEY ARGUMENTS OF HAPL**
β HAPL is eligible under **Regulation 3.2** of the Distribution Open Access (DOA) Regulations (Contract Demand > 1 MVA).
β The **DOA (Second Amendment) Regulations 2023** (effective 10 November 2023) **deleted the 8th proviso** that earlier mandated Gross Metering during Open Access.
β New **Regulation 3.4** explicitly permits simultaneous Open Access and Net Metering for eligible consumers.
β MSEDCLβs continued Gross Metering billing is **contrary to the amended regulations**.
β HAPL had repeatedly requested MSEDCL to allow Net Metering (JanβJuly 2025) but received no response.
β MSEDCLβs reliance on its own **Clarification Petition (Case No. 232 of 2024)** is misplaced as the regulation is already in force.
β
### **4. MSEDCLβS DEFENSE**
β At the time of commissioning (Nov 2022), the **DOA (First Amendment) Regulations 2019** applied, which required Gross Metering during Open Access.
β The 2023 Amendment is **prospective**, and HAPL did not apply for **Green Energy Open Access (GEOA)** through the proper **Nodal Agency (MSLDC)** as required.
β MSEDCL filed **Case No. 232 of 2024** seeking clarification on the interpretation of Regulations 3.3 and 3.4, which is still pending.
β Until clarity is provided, existing billing (Gross Metering) continues.
β HAPLβs failure to comply with GEOA procedure renders its claim invalid.
β
### **5. MERCβS ANALYSIS & RULINGS**
#### **a) Regulatory Framework (Issue a)**
β The **8th proviso of the 2019 Regulations** (requiring Gross Metering during Open Access) was **deleted** in the 2023 Amendment.
β **Regulation 3.4** now explicitly allows **simultaneous Open Access and Net Metering**.
β Since HAPLβs Open Access started in **November 2023**, billing **must follow Net Metering** from 10 November 2023 onward.
#### **b) Compliance with Open Access Procedure (Issue b)**
β MSEDCL delayed implementing the 2023 Amendment until directed by MERC in **Case No. 129 of 2024** (Sept 2024).
β HAPL applied to MSEDCL (as Nodal Agency under earlier rules), and MSEDCL approved monthly Open Access.
β **MSEDCLβs own failure to implement the new system cannot deny HAPL its rightful benefit.**
#### **c) Overlap with MSEDCLβs Clarification Petition (Issue c)**
β In **Case No. 197 of 2024** (July 2025), MSEDCL had already **agreed to provide Net Metering adjustments** subject to the outcome of its clarification petition.
β MERC held that **MSEDCL cannot discriminate** between similarly placed consumers.
β The regulation is **in force**, and MSEDCL must comply.
β
For more information please see below link: