BHEL issue Tender for Setting Up of 1.3 MW AC Grid Connected Solar PV Plant at Bharat Heavy Electricals Ltd Factory Situated In U.P. β EQ
Summary:
β
### **1. SCOPE OF WORK (SPD RESPONSIBILITIES)**
β **End-to-End Development**: Design, supply, installation, commissioning, O&M for 25 years.
β **Civil & Structural Works**: Roof strengthening, permanent ladders, drainage, waterproofing.
β **Grid Connectivity**: Evacuation up to BHELβs substation, including transformers, cables, metering infrastructure.
β **Safety & Monitoring**: CCTV, monkey protection, SCADA, weather monitoring, RFID tagging of modules.
β **Compliance**: All statutory clearances, permits, labor laws, GST, insurance.
β **Water & Auxiliary Power**: Water provided by BHEL at chargeable rates; auxiliary power drawn from grid and netted off.
β **Site Handover**: After 25 years, SPD must either remove plant or hand over in working condition to BHEL at no cost.
β
### **2. BIDDING PROCESS & ELIGIBILITY**
β **Bid System**: Single-stage, two-envelope (Techno-Commercial & Financial).
β **Eligible Entities**: Indian companies, consortia, foreign companies (must form Indian SPV with β₯51% holding). LLPs not eligible.
β **Pre-Qualification Criteria**:
β **Technical**: Minimum 500 KWp rooftop/land solar plant installed and operational for β₯1 year in last 7 years.
β **Financial**:
β Net Worth β₯ βΉ133.64 Lakhs.
β Avg. Annual Turnover β₯ βΉ267 Lakhs (last 3 years) OR Line of Credit β₯ βΉ167 Lakhs.
β **Experience**: Must provide PO/work completion certificate.
β **EMD**: βΉ5 Lakhs (valid 6 months).
β **Performance Bank Guarantee**: βΉ33.8 Lakhs (βΉ20.8L for Jhansi, βΉ13L for Varanasi) before PPA signing.
β
### **3. BID EVALUATION & SELECTION**
β **Techno-Commercial Evaluation**: Compliance with NIT, site visits, document verification.
β **Financial Bid**: Tariff quoted up to two decimals.
β **Reverse Auction**: E-auction for shortlisted bidders (BHEL may decide not to conduct).
β **Selection Criteria**: Lowest tariff (L1) selected; tie-breaker based on earlier bid timestamp.
β
### **4. KEY CONTRACTUAL & COMMERCIAL TERMS**
β **Tariff**: Fixed for 25 years, inclusive of all taxes (except future Change in Law).
β **Change in Law**: Compensation mechanism via Appropriate Commission; excludes corporate tax changes.
β **Capacity Utilization Factor (CUF)**: Minimum CUF as per Annexure-J (declining from 16.85% in Year 1 to 13.50% in Year 25).
β **Generation Shortfall**: SPD pays compensation = (DISCOM tariff β PPA tariff) Γ shortfall energy.
β **Excess Generation**: BHEL may purchase excess unless refused; SPD cannot sell to third parties without BHELβs written consent.
β **Commissioning Timeline**: 6 months from PPA effective date.
β **Delay Penalties**:
β Up to 1 month: 20% PBG encashed.
β 1β3 months: Remaining 80% PBG encashed.
β Beyond 3 months: BHEL may terminate PPA.
β **Financial Closure**: Within 3 months of PPA; delay charges @ βΉ1000/MW/day + GST.
β
### **5. LEGAL & STATUTORY HIGHLIGHTS**
β **GST Compliance**: Mandatory; invoices must match GSTR-2B for credit.
β **Statutory Duties**: PF, ESI, Bonus, Gratuity, Labour Welfare Fund, etc., as per BHEL norms.
β **Dispute Resolution**:
β First: Amicable settlement via BHELβs Designated Engineer.
β Then: Conciliation as per BHEL Conciliation Scheme 2018.
β Arbitration: Through India International Arbitration Centre (IIAC), New Delhi (for disputes < βΉ10 Cr).
β **Jurisdiction**: Exclusive courts in Jhansi/Varanasi.
β **Liability Cap**: Limited to contract price except for fraud, willful misconduct, or IP infringement.
β
### **6. DOCUMENTATION & FORMATS**
β **Mandatory Formats Provided**:
β Covering Letter, Power of Attorney, Financial Requirement, PBG, Board Resolutions, Consortium Agreement, Technology Declaration, No Deviation Certificate, etc.
β **Submission**: Online via GePNIC portal; digital signature required.
β
### **7. TECHNICAL SPECIFICATIONS**
β **Modules**: Must be from MNREβs Approved List of Models & Manufacturers.
β **Warranty**: Modules β 90% output after 10 years, 80% after 25 years; Inverters β 5 years warranty.
β **Standards**: IEC/BIS compliance for modules, inverters, cables, connectors.
β **Monitoring**: SCADA, real-time data to BHEL, RFID tracking for modules.
β **Disposal**: E-waste rules compliance for end-of-life modules.